Powerline Stringing - Dulacca Wind Farm

Powerline Stringing - Dulacca Wind Farm

Composite Matting on Powerline Stringing Works

JWA assisted in connecting the 180MW Dulacca Windfarm, home to Australia's tallest wind turbines standing at 230 metres in height, to the national electricity grid. The project required access and working platforms in sensitive agricultural land and Dura-Base Composite Mats was selected as the cost-effective alternative to traditional crush rock.

Project challenges

  • Accessibility during rainy season and maintaining project progress
  • Minimising the impact and respecting integrity of private agricultural land
  • Ability to modify working platform as and when needed

Benefits of Composite Matting

Site team installed 560 Dura-Base mats (equivalent to 1.2 km of road) in just one week, saving significant time compared to traditional rock methods, which would have taken 4-5 weeks.

The project made use of 4,700m² of composite mats for temporary roadway and safe work platforms. According to calculations by JWA, considering the standard 300 mm thickness of gravel base typically used for construction access, the utilisation of mats saved approximately 2,818 tons of crushed rock. To put it in perspective, this equates to about 232 loads of 24-ton dump trucks, as opposed to just 22 semi-trailers needed for transporting the mats - both to and from site. This significantly reduces not just the need for quarried material, but also the carbon emissions from transportation.

Resource Conservation

  • Savings of approximately $550,000 in quarried material costs.
  • Elimination of 60% of the estimated costs associated with rock access.
  • No need for additional top-ups after heavy rain 

Emission Reduction

  • Delivery and pickup of mats saved on 210 truck trips, cutting down on transport emissions compared to usage of quarried material. 

Minimised time on site

  • Installation and removal of the roadway using mats took only 15 days, whereas traditional rock access would have taken 50 days.

Soil Conservation

  • The remediation process after mat removal involved recultivating the land as part of normal cultivation practices, avoiding the need for mechanical removal of imported materials, reinstating removed soil, and achieving compaction levels suitable for safe agricultural machinery traffic.
  • Eliminated the risk of cross-contamination to the sensitive agricultural land. 

Using Dura-Base mats helped reduce the resources required, the time and the cost of the delivery of the works package that saw the wind farm being connected to the grid on schedule.

Do you have a project span over kilometres of challenging terrain? Our experienced team is ready to discuss your scope of work today.

Enquire now

Case Study Attributes

Project Name
Powerline Stringing - Dulacca Wind Farm
industry
Renewables
Location
Dulacca, QLD
applications used
Sensitive Site Access, Soft Ground Access, Ground Protection, Work Platforms
  • Bogmats for low impact access into agricultural lands
    prevBogmats for low impact access into agricultural landsnext
  • Reusable Work Platforms for Powerline Stringing Works
    prevReusable Work Platforms for Powerline Stringing Worksnext
  • Double layers of composite mats for additional load spread
    prevDouble layers of composite mats for additional load spreadnext
  • Composite roadway mats with minimal topsoil disturbance
    prevComposite roadway mats with minimal topsoil disturbancenext
  • Modular work platforms with flexible layouts
    prevModular work platforms with flexible layoutsnext
  • 420 sqm per 24t trailer
    prev420 sqm per 24t trailernext

How can we help you?

Talk to one of our experienced team about your project needs. Whether it is to review ground conditions, load capacities or just after a quote, click here and our team will be in touch.

Enquire now

Our Clients and Major Projects

  • CPB
  • John Holland
  • Queensland Rail
  • Powerlink
  • Level Crossing Removal Project
  • Commonwealth Games 2018
  • WCnnx
  • WestGateTunnelProject
  • Santos
  • Chevron
  • Exxon Mobil
  • Origin
  • Arrow Energy
  • QGC
  • Schlumberger
  • Oil Search
  • Weatherford
  • Woodside
  • Spiecapag
  • RioTinto